PAISLEY – The Teeswater River Bridge replacement project, located on Bruce Road 3 in Paisley, will begin on Monday, May 2.
The existing bridge location will be closed from July 1 to approximately Aug. 31, 2023 during construction.
The project will start in May with the construction of a temporary bridge that will connect Goldie Street and Church Street, over the Teeswater River, and serve as the connecting detour for motorists and pedestrians in Paisley. Signage will be in place. The businesses of Paisley are open and remain fully accessible.
The new Teeswater River Bridge being constructed will be an integral abutment style bridge with two 23-metre spans with a middle pier. The design will allow for more river flow clearance and will have a service life of 75 years.
This construction project will also include work by the Municipality of Arran-Elderslie, scheduled for 2023 on Queen Street, north of the bridge. This infrastructure work will include water mains, sanitary and storm sewers, sidewalk rehabilitation, and road paving.
Semi-trucks, tractor trailers, and agricultural equipment are required to avoid crossing at the Teeswater River Bridge in Paisley during the construction period due to the tight turns of the in-town detour. These large vehicles are encouraged to move east-west using Highway 40, Highway 9, and Highway 4, and north-south using Highway 19, Highway 10, and Highway 21. Businesses using large trucks for shipments and deliveries are encouraged to make alternative route plans to avoid the in-town detour.
The Teeswater River Bridge in Paisley was constructed in 1935 and provided over 85 years of service to the community. Looby Construction Ltd. is the contractor for this construction project and BM Ross is the project engineer. Partial funding for this project is provided by the Canada Community Building Fund.
Projected Timeline
- Temporary bridge construction – May 2022 to July 2022.
- Temporary bridge in operation – July 2022 to August 2023.
- Old bridge demolition/new bridge construction – July 2022 to August 2023.
- New infrastructure construction north of new bridge – starting in 2023.
- Temporary bridge demolition – starting in September 2023.